
The following document provides information about setting up, planning for, and managing a multi-project scenario using POD .You will find a detailed case study and hands-on illustrations to plan a project step by step using the Multi-project feature.
Multiprojecting is one of the best ways to manage large and complex projects. This feature provides various advantages over the traditional approach, few of which are listed below.
Functional Advantages:
The Multi-project feature can be used in breaking down large
and complex projects into efficiently manageable smaller subprojects which are
owned by respective Project Managers/Functional leads. The Multi-project feature
enables Program Managers to setup a main project including multiple smaller
subprojects and establish cross project links between subprojects at the task
and summary level. These links specify the logical sequence of events among the
subprojects. This feature allows Program Managers to have a panoramic
view of the entire Program. Program execution and control is
made lot simpler when compared to the traditional approach.
Each Subproject when
opened separately contains the cross project predecessor task information to
help individual PM’s / leads to communicate effectively. Cross linking between
subprojects helps Program Managers to arrive at an optimal Project schedule for
complex projects.
Observing effects of changes/updates made to the subprojects by respective project managers on the overall program schedule and monitoring overall program progress is made simple when using the Multi-project feature. For example, a software engineer might need more time to complete a certain task in the coding phase which is supervised by the software manager as a separate subproject. Accepting the change would effect the release date of the product. In the Multi-project scenario, the overall effect of this change can be immediately seen as the coding subproject is inserted into the multi project and linked in a structured hierarchy.
Using the Multi-project feature, subprojects or unrelated projects can also be consolidated together to give a panoramic view of all the projects on an enterprise level. Program Managers can view and print custom reports of all the projects combined together. The Multi-Project feature allows Managers to view key details of projects in relationship to each other. It helps Program Managers to easily view status details at individual subproject and overall program levels.
This feature also helps Resource Managers to locate where there resources are working. With the advanced Histogram feature included in POD, Resource Managers can now view the Resource’s assignment details at task, project and program level. The Histogram feature provides options to view resource assignment information for the selected tasks, selected project and other projects along with a line of availability making Resource Managers task simpler.
Technical Advantages:
The Multi-project feature
adds significant value by reducing the system load as complex projects need not
be opened by participating Project Managers for monitoring and controlling
purposes. They can work on there own individual subprojects without having to
open the main project file. The changes made are automatically updated into the
overall program file once they are saved. This significantly reduces system
latency. Coupled with the availability of the application over the internet
through the On-Demand ecosystem in any part of the world, managing global
projects on the fly is a reality.
The Multi-project feature resolves another major bottle neck
in collaborative environment. In traditional approach, the entire project is
locked by the manager when he is working on some part of the project file he is
responsible for making it unavailable to other Managers and higher-ups
simultaneously. In the Multi-project scenario, as the phases are split into
subprojects and are owned by individual managers, each manager works on his own
sub-project thereby increasing the availability of the main Project file.
In the Multi-project scenario, delegating of responsibility to individual work package owners / managers through sub-projects inspires commitment, ensures accountability and makes tracking of finer details of project easier.
Esparto Capital Equipments Inc (ECEI) is a large scale turnkey
equipment manufacturing company having a global presence with offices in
multiple countries operating in different time zones. Teams situated in
different geographic locations play vital roles in the project lifecycle.
Project-ON-Demand solution was adopted by Esparto Capital Equipments Inc to globally manage there projects involving multiple time zones, cultures, languages etc. ECEI has adapted POD for the following reasons
o Complete Project Management Solution.
o Short implementation lead time.
o No upfront technical overheads and integration issues across different countries/offices.
o Advanced multi-project and Histogram features.
o Email Collaboration, Timesheet/Calendar functions.
The “Chemical Reactor” project lifecycle involves the following critical phases:
o Process design to develop the equipment specs – Location: USA.
o Detailed engineering to develop the manufacturing drawings – Location: INDIA
o Equipment manufacturing – Location: Japan
o Installation and commissioning– Location: Middle east
The Program is centrally monitored from the program office situated in Texas.

A simple work breakdown structure for the above program is depicted below:

The Program Manager
receives the charter and prepares the high level plan. He finalizes the high
level project structure, roles and responsibilities and major milestones
which are depicted in the table below:
|
ID |
Description |
Duration |
Responsibility |
|
|
Program Management Program Planning
|
9 Months |
Program manager |
|
sp1 |
Process design Requirements
analysis |
6 Weeks |
Process manager |
|
sp2 |
Detailed Design Engineering |
6 Weeks |
Engineering manager |
|
sp3 |
Manufacturing Ordering of
material |
9 Months |
Production manager |
|
sp4 |
Installation & Commissioning Piling and
Foundation |
3 Months |
Site Manager |
Using POD, individual managers create detailed project plans from there respective offices and upload them using Project-ON-Demand solution.
For example, the Production Manager operating from Japan creates a detailed project plan for the Equipment manufacturing phase as seen below and saves it:

These individual project plans are then integrated into the overall program plan by the Program Manager operating from Texas, USA. The overall program plan once integrated looks similar to the plan shown below:

The Program Manager integrates individual subprojects into a program plan by linking tasks and phases in a structured hierarchy to arrive at a complete program plan. When respective project managers open there projects, the cross project links are also shown in there plans. For example, opening the Manufacturing Subproject shows the following cross project task dependencies:
Note: Cross project tasks dependencies are denoted by gray links.
When the main project file is saved, individual team members assigned to the tasks receive E-mail notifications. Team Members can update task progress can from www.projity.com. These updates are automatically added to the subproject/main project when they are opened.
As mentioned earlier, the Advanced Histogram feature allows the Managers to view enterprise level resource allocation information in the form of graphs. To know more about the Histogram feature click here.
The following steps details the procedure to use the Multi-projects feature in POD.
To insert a subproject into a main project, Click on Insert, Project. This will insert the project and open it as a special “subproject” task which almost works like a parent task. The children of this task are the tasks in the subproject.

When a project that is open in another window is inserted into the current project, the other window is closed and its project is used as the subproject. POD safeguards Project Managers from inserting the same project twice into another.
Opening a Sub-Project:
In POD, if a main project containing subprojects is opened, the subproject isn’t opened till it is expanded. The subproject task which is displayed will however show the updated dates even when not opened.

All unopened subprojects are marked read-only. An opened subproject
has a green + sign to expand or contract it. All unopened project have a red + sign.
POD also displays a special indicator icon to highlight inserted subprojects.
When a main project containing subprojects is saved, all opened subprojects that are not read-only are also saved automatically. To save a Multi-project file, click File – Save.
In the Projects View, subprojects automatically appear under their parent project. Individual subproject details like Start, End, Cost, Work, Actual work are seen here along with the rolled up values for the entire Program.

The Multi-project feature enables links between tasks in a parent project and a subproject or between subprojects that live in the same master. These external links show up in gray when the individual subprojects are opened.
One cannot link to an external task as it is “read-only”. If the real task for an external task is opened in a sibling subproject, the gray task is removed and the link is drawn to the real task.

Special Indicators: Invalid Subproject
Under complicated circumstances with nested subprojects, one could conceivably have a subproject included twice in the main project. One can also rarely have projects include each other or themselves (via an intermediate project). In these circumstances, POD will disable this subproject and show a special indicator. Moving the mouse over the indicator shows “This subproject is not valid: It can only be inserted once in a consolidated project”.

Circular Task Relationship:
In certain complicated scenarios, one can have a circular link produced by opening a subproject. In such cases, POD warns the user and disables the link automatically. These links are denoted by grey dashed lines.
